#1020: How long does the implementation take?

Отредактирована: сегодня

Question

How long does the implementation take?

Answer

The duration depends on the number of processes, integrations, migration volume, and infrastructure requirements. Basic setup without complex migration takes significantly less time than a corporate project with multiple environments and external systems.

The implementation plan is formed after a brief assessment. For a project with migration, the typical scheme includes 1-3 days for audit and data matching, 2-4 weeks for transfer and setup, about a week for verification, and 3-5 days for training before launch. The deadlines depend on the capabilities of the source system and the readiness of accesses.

Details: How long does the implementation take? · How migration proceeds